The practice and legal grounds for implementation of the authorities of executive body — Rostechnadzor, is analyzed in the article. Rostechnadzor issues a permit for admission to the operation of the electrical installations during their technological connection. The article considers the categorization of the applicants who need to obtain a permit from Rostechnadzor for admission to the operation of electrical installations. It is done in accordance with the permissible power of the electrical installation and the required category of power supply reliability. The applicants or individuals (without the status of an individual entrepreneur) are included into a separate category. This is done for simplifying the procedure for technological connection in terms of the requirements and subsequent receipt of a permit for electrical installation commissioning. The issues are highlighted related to the organization by Rostecnadzor of issuing permits for admission to the operation of electrical installations and the transition to a subject-oriented model in relation to issuing permits for admission to operation.
The main violations are shown, which were identified by Rosteсhnadzor specialists when reviewing the documents of the applicants and inspecting the electrical installations allowed for operation. The main criterion for checking the technical feasibility of technological connection in the form of limiting the electrical installation throughput is given. The need in admission of power receivers is substantiated based on their rated power and the introduction into the Rules for Technological Connection of Power Receivers of the requirement for obtaining permit from Rostechnadzor for admission to operation at each stage of power receivers commissioning based on their maximum capacity in totality on all the stages. If the applicants need to obtain a permit from Rostechnadzor for admission to operation, then the grid organizations are recommended to clarify Rostechnadzor requirements and these rules.
- Implementation of the activities when issuing permits for admission to the operation of thermal and electrical power plants: reference and methodological manual. Мoscow: ZAO NTTs PB, 2016. 64 p. (In Russ.).
- Reference and methodological recommendations for study and application of the Rules for the technical operation of electrical Installations consumers. In 3 parts. Pt 1. Section 1. Organization of electrical installations operation (with 33 additional reference materials). Saint Petersburg: ChOU DPO «NTTs «Aksioma Elektro», 2015. 158 p. (In Russ.).
- General information about technological connection. Available at: https://minenergo.gov.ru/node/545 (accessed: March 15, 2020). (In Russ.).
- Technological connection to electrical grids. Methodological guide for the entrepreneurs. Available at: http://www.consultant.ru/document/cons_doc_LAW_92102/e3e41c2d374babe4e5290cdbc47a33d45c6ea340/ (accessed: March 10, 2020). (In Russ.).
- Clarifications on certain issues about the procedure for technological connection to power grids. Available at: https://fas.gov.ru/documents/575884 (accessed: March 20, 2020). (In Russ.).
- Semenovich K.S. Contract of technological connection to power grids: thesis... Candidate of Legal Sciences. Saint Petersburg: SPbGU, 2017. 313 p. (In Russ.).
- Leukhina E.E. Legal regulation of supervisory activities in the field of ensuring safety in the electric power industry: thesis... Candidate of Legal Sciences. Chelyabinsk: YuUrGU, 2014. 219 p. (In Russ.).
- Nozdrachev A.F. Permissive system in the Russian Federation: scientific practical manual. Мoscow: INFRA-M, 2015. 928 p. (In Russ.).
- Favorable business environment. Russian Federation. Available at: https://russian.doingbusiness.org/ru/data/exploreeconomies/russia (accessed: April 1, 2020). (In Russ.).
- Rules for technical operation of consumers electrical installations: order of Minenergo of Russia dated January 13, 2003 № 6. Available at: https://base.garant.ru/12129664/ (accessed: March 22, 2020). (In Russ.).
- Rules for technical operation of the power plants and electric grids of the Russian Federation: order of Minenergo of Russia dated June 19, 2003 № 229. Available at: https://base.garant.ru/186039/ (accessed: March 23, 2020). (In Russ.).
- On the electric power industry: Federal Law of March 26, 2003 № 35-FZ. Available at: http://www.consultant.ru/document/cons_doc_LAW_41502/ (accessed: April 30, 2020). (In Russ.).
- About amendments to the certain legislative acts of the Russian Federation on the issues of admission to power plants commissioning: draft law № 754049-7. Available at: https://sozd.duma.gov.ru/bill/754049-7 (accessed: April 30, 2020). (In Russ.).
- Rules for the technological connection of power receivers of electric energy consumers, objects for the electric energy generation, as well as objects of the electric grid facilities belonging to the grid organizations and other individuals, to power grids: Decree of the Government of the Russian Federation dated December 27, 2004 № 861. Available at: http://www.consultant.ru/document/cons_doc_LAW_51030/fda4f3a4823b22f35baf202e191aa8ea59e77b9e/ (accessed: April 30, 2020). (In Russ.).
- Code of the Russian Federation on administrative infractions. Available at: http://www.consultant.ru/document/cons_doc_LAW_34661/ (accessed: April 2, 2020). (In Russ.).
- About the amendments to some acts of the Government of the Russian Federation on improving the procedure of the consumers technological connection to electric grids: Decree of the Government of the Russian Federation of April 21, 2009 № 334. Available at: http://www.consultant.ru/document/cons_doc_LAW_87100/ (accessed: April 30, 2020). (In Russ.).
- Administrative regulations for the provision by the Federal Environmental, Industrial and Nuclear Supervision Service of the state service on issuing permits for the admission to operation of power receivers of electric energy consumers, objects for electric energy generation, as well as objects of the electric grid facilities belonging to the grid organizations and other individuals (in cases stipulated in the regulatory legal acts of the Russian Federation): draft. Available at: https://www.garant.ru/products/ipo/prime/doc/56612721/ (accessed: April 30, 2020). (In Russ.).